Update: Maelfa Redevelopment

Below is useful information about the next steps in the programme of regeneration taking place in Llanedeyrn. The update is seperated into three sections, with the next steps of each aspect of work detailed below.

If you require any further information about the redevelopment or any changes that will be in place during the regeneration work, please dont hesitate to contact me using jo.stevens.mp@parliament.uk. 

Maelfa Redevelopment:

                        maelfaupdate.jpg

  • Phase 1 demolition (southern wing, plus former library) is programmed to start in February
  • Community engagement event by Jehu to be held in January 2017, publicising phasing, timescales and access arrangements.
  • Temporary footpath diversion work.  All access to the Maelfa shops and flats will be from the northern( Powerhouse) end. Routes will be publicised in advance and sign-posted.
  • Temporary relocation of inward-bound bus stop - to be discussed with bus operators.
  • Construction start by Persimmon Homes in January.
  • Closure and infilling of Roundwood underpass.
  • Agreement on Heads of Terms for leases of other new retail units.
  • Demolition of Family Centre. Agreement on disposal to Persimmon Homes

 

Powerhouse Redevelopment:

                     powerhousredev.jpg

 

  • Programme of works runs to May, 17.
  • Hoarding art project involving Springwood Primary.
  • Finalisation of lease with Police and Crime Commissioner for first-floor accommodation.

 

Maelfa High Rise Refurbishment:

                        maelfarefurbhighrise.jpg

 

  • Planning permission for refurbishment works granted in October.
  • Detailed design and specifications being prepared for tender package.
  • Heads of Terms agreed with Churches Together for ground-floor community unit.
  • Phasing and sequencing of interface works between tower-block and main redevelopment scheme being investigated.
  • Discussions with telecom operators on roof-scape works.
  • Issue of tender invites to contractors on SEWSCAP framework.
  • Projected site start summer, 17, subject to contractor appointment.

Reactions

Please check your e-mail for a link to activate your account.

The Labour Party will place cookies on your computer to help us make this website better.

Please read this to review the updates about which cookies we use and what information we collect on our site.

To find out more about these cookies, see our privacy notice. Use of this site confirms your acceptance of these cookies.